Round form material planning

Sonotube Concrete Calculator

How much concrete and how many tubes do you need?

A Sonotube concrete calculator is a material planning tool for identical round forms. Enter a product line, nominal diameter, height below and above grade and form count to get concrete volume, a +1 in diameter check, a stock tube cut plan and whole-bag counts.

Form lines
Builder's Tube · Round · Commercial
Nominal sizes
6 to 60 in, by line
Outputs
yd³ · stock tubes · bags
Data checked
September 27, 2026

Interactive calculator

Calculate concrete and stock tubes

Pick a product line to filter sizes. Choose Other or measured form for a measured inside diameter or another stock length.

US + metric inputs
Form product
Recorded product-line sizes
Height and form count

For a column poured from the top of a footing or slab, enter 0 below grade and the full height above grade.

Selected bag yield
Planning inputs
%
Allowance boundary

The percentage is a user-selected scenario, not a universal recommendation.

Trademark and affiliation notice: Independent third-party calculator. Sonotube, Builder's Tube and RainGuard are Sonoco trademarks used here only to identify the referenced concrete forms and public product data. This site is not sponsored, endorsed by or affiliated with Sonoco Products Company or SPC Resources, Inc.

Transparent method

How the Sonotube concrete calculator plans volume and cuts

The volume calculator's round branch takes diameter, height and quantity. This Sonotube concrete calculator adds product-line sizes, tube cut plans, a +1 in diameter check and two bag-rounding methods. The +1 in check never changes the order volume.

  1. 01

    Pick the form line or measure it

    Each product line limits the diameter and stock length lists. Other or measured form takes your own sizes.

  2. 02

    Add the two height measurements

    Measure form bottom to grade, then grade to top. For columns on footings or slabs, enter 0 below grade and full height above.

  3. 03

    Read the cut plan before buying tubes

    Short forms share tubes: stock length divided by form height, rounded down. Taller forms use full lengths first, then share tubes for the remainder.

  4. 04

    Apply allowance before rounding bags

    The Sonotube concrete calculator applies allowance to concrete only. Pooled bags round the total once; separate-form bags round each form, then multiply.

Sonotube Concrete Calculator calculation formulas
OutputFormula
One formπ × (diameter ÷ 2)² × (height below grade + height above grade)
Order volumeone-form volume × form count × (1 + allowance ÷ 100)
Oversize checkπ × ((nominal diameter + 1 in) ÷ 2)² × form height × form count
Stock tubesceiling(form count ÷ pieces per tube), pieces per tube = floor(stock length ÷ form height)
Four plain brown cardboard forms in backyard soil beside a string line, with fresh concrete in one form and a shovel and wheelbarrow nearby
Generic paper forms illustrate heights below and above grade, not a recommended pier design.

Field context

Measure the full concrete height inside each form

Enter height below and above grade in the Sonotube concrete calculator. Measure stock tube length separately.

The image shows generic unbranded paper forms, not a manufacturer photo, logo or package. Forms called sono tubes or concrete tubes need the same two height measurements.

Check the arithmetic

Worked example: six 12 in forms, each 4 ft tall

At 0% allowance, one 12 in form 4 ft tall holds π × 0.5² × 4 = 3.141593 ft³ = 0.116355 yd³. Six forms hold 18.849556 ft³ = 0.698132 yd³ ≈ 0.534 m³, shown as 0.70 yd³.

At 13 in, one form holds 3.687008 ft³ and six hold 22.122048 ft³ (0.82 yd³), 17.4% more. That is a what-if check, not a claim that every 12 in form measures 13 in.

The QUIKRETE 80 lb record declares 0.60 ft³ per bag. Pooled, six forms need 31.4159 bags, rounded once to 32. Per form, 5.236 rounds to 6, so 6 × 6 = 36 bags.

Builder's Tube 4 ft stock needs one tube per form, six in all. Each 12 ft Round tube gives three 4 ft pieces, so two tubes cover six forms with 0 ft of offcut.

Concrete per foot of form height by nominal diameter
Nominal diameterft³ per ftft³ per ft at +1 inAdded volumeHeight per yd³
6 in0.1960.26736.1%137.51 ft
8 in0.3490.44226.6%77.35 ft
10 in0.5450.66021.0%49.50 ft
12 in0.7850.92217.4%34.38 ft
16 in1.3961.57612.9%19.34 ft
24 in3.1423.4098.5%8.59 ft
36 in7.0697.4675.6%3.82 ft
48 in12.56613.0954.2%2.15 ft

Use the result correctly

Three checks before using the quantities

  1. 01

    Nominal size is not a measured inside diameter

    Sonoco's FAQ says the inside diameter will be at least the stated size and can be up to 1 in larger. Outside diameter usually runs 1/2 to 1 in over the tube size, with up to 2 in possible. Builder's Tube literature calls for measuring when diameter is critical. Enter the inside diameter in measured mode.

  2. 02

    Choose a bag count that matches allocation

    Pooled rounding sums forms first. Separate-form rounding assigns whole bags per form for pours on different days.

  3. 03

    Take structural dimensions from project information

    Diameter, base size, reinforcement and capacity come from project drawings and a licensed engineer or architect, not this tool. Confirm pier depth with the local code inspector or a licensed structural engineer. Sonoco also states that the paper form is not load-bearing.

Sources and assumptions

Reference record

Sonotube data were checked September 27, 2026 for North America. Only 4 ft Builder's Tube stock is listed because Sonoco documents differ on longer lengths. We calculate the per-foot table.

Questions before ordering

Sonotube Concrete Calculator FAQ

How many bags of concrete does a 12 in Sonotube need?

For a 4 ft form at 0% allowance, the QUIKRETE 80 lb record (0.60 ft³) gives 5.236 bags, so 6 per form. Six forms need 32 bags rounded once or 36 rounded per form. Other bag records change the count.

Is a 12 inch Sonotube exactly 12 inches inside?

No. Sonoco calls its diameters nominal: the inside is at least the stated size and up to 1 in larger. Enter your measurement in Other or measured form.

How many forms can I cut from one stock tube?

A 12 ft tube gives three 4 ft pieces or two 5 ft pieces. The plan excludes saw kerf, damaged ends and splice collars.

What sizes do Sonotube forms come in?

In this tool, Builder's Tube covers 6, 8, 10 and 12 in with 4 ft stock. Round covers 6 to 36 in with 12 ft stock. Commercial covers 6 to 60 in with 12 and 20 ft stock. Store inventory varies.

Is this an official Sonotube calculator?

No. This Sonotube concrete calculator is independent and unaffiliated with Sonoco Products Company or SPC Resources, Inc.

Planning boundary

What this result does not decide

This Sonotube concrete calculator does not set diameter, depth, reinforcement or capacity. It skips enlarged bases, and product-line notes do not approve formwork.